Construction of 12,742Km Awa Iman-Asong-Ikot Edim-Ikot Emem Road with 2 Bridges in Onna&Mkpat Enin Local Government Areas

Phase III Road Project, construction of 12.742 Km Ikot-Emem Road with 2NO. Bridges, The project which was mobilized on 15th June 2016 to be completed by 30th June 2017. In the project, 2NO. Bridges (35m & 75m Bridges), 6.9KM Main alignment with two spurs (spur 1 1.024KM, spur 2  3.687Km ) and 230M Access Road to the Meter Company.

Project Duration

Start Date End Date Duration Status
October, 2015 March, 2018 30 Months On-going